Good progress on site has been made in the reporting period and the project remains on track for a completion 4Q23.
We are fast approaching the completion of the concrete frame, at which point we will see the dismantle of the tower crane. We expect this to be dismantled before Christmas. The concrete podium that will site the communal gardens at first floor level has also been completed.
The façade continues up the building and weather boards have been installed up to and including level 6 on Block A, this makes the internals significantly water tight and allows the internal fit out trades to follow in sequence. Windows have been delivered and installed to the same height. Brickwork will follow using the mast climbers that have been installed to the building’s façade.
Block B is now water tight (other than for access provisions) which is allowing the internals to progress significantly. 2nd fix elements have commenced on the 1st floor apartments and will follow through in sequence. The reporting period will see the scaffolding surrounding block B be dropped.
Internally in block A all party walls have now been erected up to and including level 4, with internal walls following quickly behind up to level 3. 1st Fix M&E has commenced in Block A and will continue up the building as more floors become available.
Activities & Trades due to commence within the next reporting period;
- Completion of Concrete Frame
- Dismantle of Tower Crane
- Completion of Brickwork to Block B
- Continuation of Block A internals
- Completion of a small cluster of apartments to Block B for snagging.
Within the period we have also nearing the completion of the first unit being the ‘benchmark unit’ which is used to ensure the high standards and quality is maintained throughout the delivery of the remaining units. We will issue a further update in due course to demonstrate the exceptionally high standards to which this development is being built.