Sky Gardens Construction Update – June 2025
The project continues to make positive progress
- The concrete frame is complete to Level 23, 1 day ahead of programme.
- Windows and weatherproofing is now complete to Level 16 and in progress on Levels 17 to 18.
- The internal partition walls are complete up to Level 10.
- First fix plumbing, electrical and ventilation is complete on Levels 2 to 8 an in progress on Levels 9 & 10 . We have now 2nd Fixed the internal walls up to Level 5 and plastering is complete up to Level 4.
- The first kitchens have been installed to Level 2 and start on Level 3 this week.
- We have also started installing the first baths and shower trays and commenced the tiling to Level 2.
- To the ground floor the sprinkler and portable water tanks have been installed and are currently being tested.
- The envelope carrier systems has commenced with bracketry, insulation and cavity fire protection to all elevations.
Next month will see further progression on all elements with new activities being installation of joinery and floor finishes. To the building envelope the external façade treatment of masonry, stone and feature metal cladding will begin to take shape.
The project remains on track for completion Summer 2026