Our Developments Sky Gardens Springwell Gardens

Sky Gardens Construction

Sky Gardens Construction Update – June 2025

The project continues to make positive progress

  • The concrete frame is complete to Level 23, 1 day ahead of programme.
  • Windows and weatherproofing is now complete to Level 16 and in progress on Levels 17 to 18.
  • The internal partition walls are complete up to Level 10.
  • First fix plumbing, electrical and ventilation is complete on Levels 2 to 8 an in progress on Levels 9 & 10 . We have now 2nd Fixed the internal walls up to Level 5 and plastering is complete up to Level 4.
  • The first kitchens have been installed to Level 2 and start on Level 3 this week.
  • We have also started installing the first baths and shower trays and commenced the tiling to Level 2.
  • To the ground floor the sprinkler and portable water tanks have been installed and are currently being tested.
  • The envelope carrier systems has commenced with bracketry, insulation and cavity fire protection to all elevations.

Next month will see further progression on all elements with new activities being installation of joinery and floor finishes. To the building envelope the external façade treatment of masonry, stone and feature metal cladding will begin to take shape.

The project remains on track for completion Summer 2026

The Mill Construction Update – June 2025

Substantial progress has been made on the Midland Mills project during May 2025. Site operations are underway and advancing on schedule.

Henley Restoration has mobilised effectively, initiating essential works on-site.

Key activities include:

  • Temporary electrics and water supplies have been installed
  • Site setup completed
  • Completion of scaffolding on accessible elevations of the West Mill
  • Internal birdcage scaffold erected for asbestos roof strip
  • Removal of defective brickwork and initiation of replacement works
  • Preparatory works for window and cill replacements

 

Sky Gardens Construction Update – November 2024

The Main Contractor began construction of the above concrete frame in the summer, and this has continued at pace. The slip form of the core has reached level 24, and the floor slabs and columns have been cast up to level 7. In addition, the drainage has been completed, and work on the external substation has begun.

Looking ahead and over the coming period the focus is on progressing the concrete frame superstructure, with completion of the slip form core planned prior to Christmas. Works on site remain on programme and will see additional trades start on the project in the new year.

Sky Gardens Construction Update – May 2024

The Main Contractor began on site at the beginning of the year. Since then all pile foundations have been completed. The formwork and reinforcement for the Tower pilecap (which also forms the Ground Floor) has been installed, and concrete is being poured in stages, and due to be complete end of the month. The reinforcement for the start of the concrete frame superstructure has been cast in at the same time. In addition, the tower crane base has been installed; peripheral drainage installation has begun, and the permanent site set up has been erected.

Looking ahead and over the coming period the focus is on erection of the tower crane and progressing the concrete frame superstructure. Works on site remain on programme and will generate an ever-increasing pace of works once the frame has progressed enough to allow follow on trades to commence on site.

Sky Gardens Construction Update – July 2022

How to contact us

Looking for a new property investment opportunity in the UK’s fastest growing city? Or want to find out more information about our residential developments and off-plan apartments for sale in Leeds city centre? 

Get in touch and let’s make it happen.


    I agree to your privacy policy



    [c4wp_nocaptcha g-recaptcha-response]

    Welcome to our new website featured image

    Latest News

    Subscribe for updates